Summary

France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.

The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.

President Macron hailed the launch as a key step for low-carbon energy and energy security.

Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”

  • Resonosity@lemmy.dbzer0.com
    link
    fedilink
    English
    arrow-up
    2
    ·
    24 hours ago

    Solar panels are glass and rare elements that we can’t recycle properly yet.

    NREL’s Solar PV fact sheet on circularity says that conventional solar PV panels have recovery rates of 80-95% given existing recycling infrastructure.

    We know how to recycle these things. The fact that we maybe don’t do so in a widespread way is because it’s still cheaper to throw shit in a landfill or incinerator.

    • TheBlackLounge@lemm.ee
      link
      fedilink
      English
      arrow-up
      2
      ·
      11 hours ago

      95% doesn’t mean you can turn 100 old panels into 95 new panels. The 5% is cobalt and stuff, that needs to be mined over and over. It’s great that we have such rates but we’re not really lacking in glass.